Wednesday, July 18, 2012

Weekly Construction Update: 7/18/2012

This week the following work is expected to be completed:
·         Install expansion joints (north plaza)
·         Form permeable concrete area on the north plaza
·         Receive delivery of granite pavers for north plaza
·         Install pavers on the west side landing (north plaza)
·         Review sample of permeable concrete on north plaza
·         Continued mechanical, electrical, and plumbing work in the ceiling grid of the Great Hall (lower level)
·         Filling/patching hole in north wall of the Lower Level
·         Continue tiling lower level bathrooms
·         Construct framing west of the lower level ramp
·         Mechanical, electrical and plumbing work in the Welcome Center
·         Installation of storefront window frames in the Welcome Center
·         Install frame soffits in the Welcome Center
·         Install door frames in the Welcome Center

Next week the following work is expected to be completed:
·         Place permeable concrete area on the north plaza
·         Install limestone on the west stairs of the north plaza
·         Begin forming and placing the planters and curbs on the north plaza
·         Continue mechanical, electrical, and plumbing work in the ceiling grid of the Great Hall (lower level)
·         Continue tiling lower level restrooms
·         Complete framing west of the lower level inside ramp
·         Plumbing work in the lower level
·         Plumbing inspection in one of the lower level restrooms
·         Drywall and tape the framed section west of the ramp
·         Continued mechanical, electrical, and plumbing work in the Welcome Center
·         Begin installation of stairs from Welcome Center to Lower Level
·         Install drop ceiling in the east section of the Great Hall