Wednesday, May 4, 2011

Weekly Construction Update: 5/4/2011

  • Demolition of the concrete on the south end of the Plaza ended today, May 4.
  • The temporary wall built in the Diocesan Center lobby will be painted tomorrow, May 5.
  • During the week of May 9, Pepper Construction will continue clearing soil and sand from the existing waterproofing on the Plaza.
  • At the same time, Pepper will begin exploration in the ceiling of the lower level in Burrill Hall and in the second elevator shaft.  This involves opening the ceiling, assessing what’s behind it, and patching it.  The exploratory work will not interfere with scheduled uses of the space.

No comments:

Post a Comment