Construction Update: 6/22/2011

Weather permitting, the following work is anticipated for next week:
  • Installation of the waterproofing Monday and Tuesday, which may produce strong odors.
  • The Peace Angel statue will be removed to storage Monday and Tuesday.
  • Concrete layout for the west stairs Tuesday through Thursday
  • Concrete pouring for the west stairs on Friday
During the following week, we expect the framing and pouring of concrete for the east stairs.