In the coming week, the following work is scheduled, weather permitting:
- Frame the east wall on Tuesday
 - Demo the plaster ceiling on the south end of the lobby on Tuesday
 - Pour concrete for the east wall Wednesday
 - Pour concrete for the west ramp Wednesday
 - Frame the west stairs Thursday and Friday
 - Install steel for the upper storefront on the south end of the lobby Thursday and Friday
 
The following week, it is anticipated that:
- The framing of the west stairs will continue and the concrete will be poured.
 - The east upper stairs and ramp will be framed and the concrete will be poured.
 