Thursday, June 30, 2011

Weekly Construction Update: 6/30/2011

In the coming week, the following work is scheduled, weather permitting:
  • Frame the east wall on Tuesday
  • Demo the plaster ceiling on the south end of the lobby on Tuesday
  • Pour concrete for the east wall Wednesday
  • Pour concrete for the west ramp Wednesday
  • Frame the west stairs Thursday and Friday
  • Install steel for the upper storefront on the south end of the lobby Thursday and Friday
The following week, it is anticipated that:
  • The framing of the west stairs will continue and the concrete will be poured.
  • The east upper stairs and ramp will be framed and the concrete will be poured.