- Concrete "cinder block" demolition on floors 2 - 4 and removal of concrete shaft
 
- Continuation of concrete block elevator shaft removal
 - Concrete "cinder block" demolition on floors 2 - 4 and removal of concrete shaft
 - Waterproofing on the north building wall (external lower level)
 - Excavation on the lower level
 - Column Footing framing & pouring on the lower level
 