This week the following work is expected:
  • Concrete "cinder block" demolition on floors 2 - 4 and removal of concrete shaft
Next week the following work is expected:
  • Continuation of concrete block elevator shaft removal
  • Concrete "cinder block" demolition on floors 2 - 4 and removal of concrete shaft
  • Waterproofing on the north building wall (external lower level)
  • Excavation on the lower level
  • Column Footing framing & pouring on the lower level