Friday, April 13, 2012

Weekly Construction Update: 4/13/2012

This week the following work was scheduled to be completed:
  • Frame walls in the lower level
  • Electrical and plumbing work in the ceiling of the lower level
  • Patching CMU (cinder block) walls
  • Setting pavers on the upper tier of the north plaza
  • Demoing and prepping the concrete slab that was the old north plaza (main plaza level)
  • Placing new concrete on the main plaza level
  • Detail framing in the link structure
Next week the following work is expected to take place:
  • Continued framing in the lower level of the 65 E Huron office building
  • Installing door frames in the lower level
  • Inspection of wall construction in the lower level
  • Continuing to set pavers on the upper tier of the north plaza
  • Install fire department piping on the upper tier of the north plaza
  • Set limestone on the upper tier of the north plaza
  • Install part of building overhand ceiling