Weekly Construction Update: 12/5/2012

This week the following work is expected:
  • Installation of Welcome Center reception desk
  • Cleaning in the Welcome Center
  • Installation of  flooring in Welcome Center vestibule & receiving area
  • Continued paver installation & caulking on the North plaza 
  • Installation of water feature including water jets and final granite on the North plaza
  • Ongoing elevator installation
 Next week the following work is expected:
  • Continued installation of the reception desk in the Welcome Center
  • Continued paver installation & caulking on the North plaza 
  • Installation of column covers on the South and North plazas
  • Elevator & Fire Department inspections