Weekly Construction Update: 12/5/2012

This week the following work is expected:
  • Installation of Welcome Center reception desk
  • Cleaning in the Welcome Center
  • Installation of  flooring in Welcome Center vestibule & receiving area
  • Continued paver installation & caulking on the North plaza 
  • Installation of water feature including water jets and final granite on the North plaza
  • Ongoing elevator installation
 Next week the following work is expected:
  • Continued installation of the reception desk in the Welcome Center
  • Continued paver installation & caulking on the North plaza 
  • Installation of column covers on the South and North plazas
  • Elevator & Fire Department inspections

Monday, November 19, 2012

Construction In Pictures: Week of 11/12/2012

Office building exterior cleaning

Office building exterior cleaning

North plaza paver install on ramp

North plaza paver install on ramp

North plaza paver install on ramp

North plaza paver install on ramp

Stripping pavement on Huron to prepare for new asphalt


Newly paved street - corner of Huron and Rush (facing east)

Welcome Center receiving area lift

Welcome Center receiving area lift with safety doors

Welcome Center receiving area lift

North plaza west end lower level door (under new Welcome Center)

North plaza west end sidewalk

North Plaza water feature wall

Welcome Center hospitality area

Welcome Center restroom with sink fixtures installed

Lower level laundry room

Lower level laundry room

Lower level laundry room

Lower level laundry room